Jan De Nul Group and Hellenic Cables Join Forces for Crete-Peloponnese Project
Jan De Nul Group and Hellenic Cables join forces for the installation and protection of a submarine power cable between the island of Crete and the Peloponnese region of the Greek mainland, developed by ADMIE.
Hellenic Cables, through its 100% subsidiary Fulgor SA, will produce the 135.7 km long cable at its Corinth plant. Jan De Nul Group is responsible for the installation of the cable in water depths up to 980 meters using its Cable Laying Vessel Isaac Newton as well as the pre- and post-lay protection works up to 600 meters water depth.
Wouter Vermeersch, Manager Offshore Cables at Jan De Nul Group: “After the successful execution of the Borkum Riffgrund 2 and Trianel export cable projects back in 2018, we are pleased to continue our good relationship with Hellenic Cables through the award of this challenging interconnection project. The cable route runs over very deep waters and a difficult seabed with extremely steep slopes.”